Beluga construction pit a

 

Thanks to our rigorous work methods and state-of-the-art equipment, we have achieved an impressive production capacity of 1,250,000 tonnes of excavated material per month. This performance testifies to our commitment to delivering superior results while meeting our customers' tight deadlines.

To maintain our efficiency and meet the growing production needs of our customers, we have invested in first-class equipment:

  • 3 CAT 6015 excavators
  • 12 x 100-tonne trucks.
  • 3 D8 tractors

We managed to mobilize three fully operational production teams in just two weeks.

Year : 2024

Contract value : 15 700 000

Contact us
Décapage beluga construction